For the week of November 16, the Town of Palm Beach scheduled pole-and-wire removal on North Ocean from Monday through Thursday, with the road closed to all but local traffic. The same notice sent drilling crews down North County Road between Seminole Avenue and Royal Poinciana Way, and it put conduit work in back yards in the blocks around Wells Road. Most of the island south of Royal Poinciana Way has already finished the same work.
Someone house hunting on Palm Beach this winter will see the town's utility project at three stages depending on the street. The stages look very different from one block to the next, and they follow a fixed order. Once you know the order, a pole, a patch of new asphalt or a lane closure tells you how long a block's work has left. On the streets north of Royal Poinciana Way, that is still measured in months, with the town now pointing to late 2027.
The town started the project in 2017. It buries every overhead power, phone and cable television line on the island and takes down the utility poles, at an estimated construction cost of $128 million to $140 million, according to the Palm Beach Civic Association's April 24, 2026 report. The island is divided into 15 zones. As of that April report, construction was finished and customers were switched over in 11 of them. Town Engineer Patricia Strayer told the Civic Association that the whole project should be done in late 2027. Each zone goes through the same steps in the same order. Crews build the underground system, customers are switched to it, the poles come down, and the streets are repaved last. The project is funded in part by a townwide special assessment the Town Council approved in 2017, which first appeared on the property tax bills mailed in November 2017.
That order lets you tell where a block stands from the curb. You can see whether a street still has poles, whether it has poles with fresh pavement marks around them, or whether it has new asphalt and no poles at all.
On the South End and in most of Midtown, the work is done. Phase 1 South runs from the south town limit up to Sloan's Curve. Phase 2 South continues from there to where South Ocean Boulevard meets South County Road, and Phase 3 South covers the stretch north to the alley below Worth Avenue. All three were complete in the April report. So were Phase 4 South, from Peruvian Avenue to Royal Palm Way, and Phase 5 South, which covers South Lake Drive, Hibiscus Avenue and the blocks between the ocean and Royal Palm Way up to Seaspray Avenue.
The last step has been paving. On April 14 the Town Council voted unanimously for $3.5 million, plus a $700,000 contingency, to Janice M Riley DBA The Paving Lady for milling and paving in three zones. One of them was Phase 4 South, between Royal Palm Way and Worth Avenue. If you are touring a Midtown house on a block that was repaved this year, its utility work is finished.
Two zones were close to finished this fall, and their streets are where the poles and wires are coming down this season.
Phase 6 South runs from Seaspray Avenue north to Royal Poinciana Way. In August the town's notices scheduled pole-and-wire removal on North County Road from Via Bethesda and Breaker Row up to Royal Poinciana, and on Royal Poinciana between North County Road and Cocoanut Row. The notice for the week of October 26 listed only "Finish any remaining punch-list items" for the zone, and the notice for the week of November 16 said no work was planned there. The April paving approval covered this zone too, from Seabreeze Avenue to Royal Poinciana Way, along with South County Road and South Ocean Boulevard down to Royal Palm Way. Separately, the Cocoanut Row watermain project was down to punch-list items in mid-November.
Phase 7 North runs from the Palm Beach Country Club up to the south side of List Road. In April its construction was done, and AT&T was moving customers to fiber. Pole removal has followed this fall. The October 26 notice scheduled it on Bahama Lane between North Lake Way and North Ocean, and in November it moved to North Ocean. The paving approved in April covers this zone from Laurian Lane to Bahama Lane, plus Bradley Place from Royal Poinciana to Dunbar Road. It also includes resurfacing the Seaview Tennis Center parking lot and resurfacing and beautifying the 100 block of Seaview Avenue between South County Road and South Ocean Boulevard. Seaview Avenue also comes up in our post on the Four Arts' season on Cocoanut Row and Seaview Avenue.
Both zones have reached pole removal, and only paving follows that step.
The last two zones are the only places on the island where the main construction is still going. They sit between Royal Poinciana Way and the start of the North End.
Phase 7 South runs from Atlantic Avenue north to Via Los Incas and Sanford Avenue. The Civic Association put it at 42 percent complete in April and said crews installing AT&T fiber conduit in Phase 7 North had slowed it down. For the week of November 16, the town scheduled service conduits in back yards at various locations. It also scheduled wire work on Bradley Place and North Lake Way between Wells Road and Sanford, and sidewalk restoration with moving lane closures on Atlantic Avenue, Dunbar Road and Wells Road between North Ocean and Bradley Place.
Phase 8 runs from Royal Poinciana Way north to Everglade Avenue. It was 19 percent complete in April and had been delayed by a significant redesign from Florida Power & Light. Phase 8 was first expected to finish in spring 2027, and the April report moved that to late 2027. The November 16 notice had directional drilling for the main conduits on North County Road from Seminole Avenue to Royal Poinciana, service connections to houses on the south side of Seminole, and tie-ins on North County Road from Everglade to Sunrise and on Atlantic Avenue between North County and North Ocean. Every item came with lane closures, and traffic was kept moving. The town adds that all of its projects are subject to change.
For a buyer, the timeline matters more than the inconvenience. A house on Seminole or Everglade bought this season will probably have drilling, then customer conversions, then pole removal and repaving around it into 2027. Eleven zones had completed that sequence as of April, according to the Civic Association. When you compare a North End house with one on a finished South End or Midtown block, count the construction months left on its street as part of what you are weighing.
Will the work still be going on during my first season if I buy on the North End? If the house is in Phase 7 South or Phase 8, between Royal Poinciana Way and Everglade Avenue or Via Los Incas, probably yes. The town's latest estimate puts the end of the project in late 2027.
How do I follow what's happening on a particular street? The town posts a weekly traffic notice on undergrounding.info that lists the phase, the work and the block, sometimes down to house numbers. Questions go to [email protected] or the hotline at 561-227-7077.
Does this affect plans to renovate after closing? The utility project runs on its own schedule, apart from the town's design and landmark reviews, which we covered in why some Palm Beach estates take twice as long to renovate. The Palm Beach neighborhood page explains how the island's areas differ.
If you are comparing a finished Midtown block with a North End street that still has drilling, The Don Moore Team can walk both streets with you and line up your timing with the town's posted work schedule. Request a Confidential Market Consultation, and we will begin with the addresses you are considering.